Site Work
Erving 38F Substation - Erving, MA
Erving, MA
Contracted to perform all drilling/blasting and crushing services for new 78,750t2 115kV switching station in the Town of Erving, MA. Drilling & Blasting Scope:Drill and blast over 36,000 cubic yards of open rock and 510 linear feet of presplit.
Crushing Scope: Process approximately 66,000 tons of 8-inch minus and 42,000 tons of 2-inch minus. Processed material used as various on-site (control) fill throughout the project.Equipment used to perform this work included a Komatsu BR580JG-1 mobile jaw crusher and a Powerscreen®1150 Maxtrak mobile cone crusher for secondary applications. /p>